Text-only Description for Workday ERP (Enterprise Resource Planning) Project Timeline
Presentation
An infographic with a horizontal timeline that is organized by month from February 2022 to February 2023 with a forward arrow.
Information
February - April 2022
- Plan
- Project
- Host discovery sessions, identify requirements and current practices
- OC&T (Collaborative Solutions' Organisational Change & Training)
- Understand organization, set key milestones and dates for deliverables
May - June 2022
- Alignment
- Project
- Gather requirements for MSU Workday design
- OC&T
- Capturing change impacts, identifying stakeholders
July - August 2022
- Configure & Prototype
- Project
- Validating MSU Denver’s Workday design
- OC&T
- Finalize Change Impacts, Roll out Communications
September - November 2022
- Test & Parallel
- Project
- Ensure Workday system is configured as designed
- OC&T
- Training Development
- Training – Late Fall
December 2022
- Plan
- Deploy
- Workday updates coming from E2E (end-to-end) testing
- OC&T
January 2023
January - February 2023 (with forward arrow)
- Post-Production
- Project
- OC&T
- Sustainment Strategy deployment
Your workday: Reimagined, Transformed, Simplified
MSU Denver logo on lower-left side of image and Workday logo on lower-right side of timeline image
Return to the Workday Project Background webpage - Project Timeline section